Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:

Access PMP Dumps Premium Version
(1975 Q&As Dumps, 35%OFF Special Discount Code: freecram)

Online Access Free PMP Exam Questions

Exam Code:PMP
Exam Name:Project Management Professional (2025 Version)
Certification Provider:PMI
Free Question Number:776
Version:v2024-08-26
Rating:
# of views:3301
# of Questions views:163476
Go To PMP Questions

Recent Comments (The most recent comments are at the top.)

Antonio - Jul 23, 2025

It is valid and helpful! I passed my PMP exam yesterday with the high points! Thanks so much! You are doing a great job, guys!

Breenda - Apr 25, 2025

Thank you so much for your high-effective PMP exam braindumps! This is an important exam for me and i had cleared it with your help. Thank you again! The certification will help me to get a better job!

Miles - Apr 25, 2025

They are the actual questions this time. Amazing dump for PMI

Noah - Mar 12, 2025

I prepared PMP exam with freecram real exam questions and passed it.

Paula - Feb 13, 2025

I used your updated version and passed PMP.

Lucien - Feb 06, 2025

Glad to tell you that Ihave passed PMP exam.

Georgia - Jan 19, 2025

You use the real talent and explores it in
right way ,and this is actually an ultimate source for the sake of preparing PMP exam.

Bernice - Jan 04, 2025

There are different choices on PMP versions, so i bought the value pack which can give me better and more experiences. The price for value pack is also low and reasonable. I successfully passed my PMP exam. Thanks!

N.K - Nov 20, 2024

No.# Option D (Review the contingency reserve) is correct because the contingency reserve is specifically allocated to address delays caused by identified risks. It can be utilized without requiring change control board approval, as it is part of the project's risk management plan and adheres to established processes.

Benson - Oct 15, 2024

Some PMP exam questions are so likely and you should pay more attention on them. Outstanding PMP exam files!

Jim - Sep 08, 2024

I have taken my PMP exams twice, but failed. My friend suggests that I can use freecram exam materials. Then I ordered the exam pdf dumps on freecram. I am so happy with the result that I passed my exam.Thanks a million!

Shirley - Sep 04, 2024

Thank you so much freecram for making my success possible in my PMP exam. I could not have done it without your help.

Gilbert - Aug 28, 2024

The price is really not cheap but I am happy to buy it. It is quite valid. Only hundreds questions. One of my colleagues buy the dumps made of 500+ questions. Really lucky.

Jerry - Aug 26, 2024

Today i have passed the PMP exam with 89%. So be brave and verify! The exam questions are mostly the same as the PMP practice questions.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
2232 viewsPMI.PMP.v2024-07-03.q171
1335 viewsPMI.PMP.v2024-05-21.q498
2989 viewsPMI.PMP.v2023-10-10.q253
10724 viewsPMI.PMP.v2022-07-17.q478
6613 viewsPMI.PMP.v2022-04-02.q436
3110 viewsPMI.PMP.v2022-03-01.q365
2193 viewsPMI.PMP.v2022-02-28.q231
2909 viewsPMI.PMP.v2022-02-01.q251
3073 viewsPMI.PMP.v2021-11-23.q161
3219 viewsPMI.PMP.v2021-11-17.q210
4833 viewsPMI.PMP.v2021-08-21.q133
2241 viewsPMI.PMP.v2021-06-27.q182
2705 viewsPMI.PMP.v2021-05-06.q96
2253 viewsPMI.PMP.v2021-05-04.q62
1842 viewsPMI.PMP.v2021-04-21.q138
1951 viewsPMI.PMP.v2021-03-29.q180
1939 viewsPMI.PMP.v2020-12-20.q134
2064 viewsPMI.PMP.v2020-10-30.q336
2401 viewsPMI.PMP.v2020-10-04.q300
2075 viewsPMI.PMP.v2020-09-10.q255
2546 viewsPMI.PMP.v2020-08-14.q299
2181 viewsPMI.PMP.v2020-06-11.q185
2149 viewsPMI.PMP.v2019-05-17.q1011
1833 viewsPMI.pmp.v2018-11-12.q1030
1960 viewsPMI.PMP.v2018-04-10.q900
3412 viewsPMI.PMP.v2017-12-15.q3515
Exam Question List
1 commentQuestion 1: A project is experiencing delays due to identified risks Wha...
Question 2: Vendor A submitted a bid for US$500,000. There is a 65% prob...
Question 3: A new project has been kicked off following a planning sessi...
Question 4: During project execution, a project manager discovers that t...
Question 5: A project team created user stories after understanding the ...
Question 6: A project team member, who is inexperienced in system develo...
Question 7: A financial company is developing a new application for mobi...
Question 8: A project manager receives a serious complaint from a functi...
Question 9: A senior vice president requested the creation of more agile...
Question 10: In a highly politicized organizational environment, the stak...
Question 11: A company is starting a critical project with a strict deadl...
Question 12: A project manager is using a hybrid approach for project del...
Question 13: A project manager is evaluating a project and realizes that ...
Question 14: A project manager is assigned to a new water treatment plant...
Question 15: A project team's performance has declined for the last three...
Question 16: A project team Is working on a relative-weighting approach t...
Question 17: A project manager is assigned to a time-bound internal proje...
Question 18: A new agile team is having trouble completing tasks. There a...
Question 19: A project manager is leading a major water pipeline project ...
Question 20: A junior staff member was recently assigned to the team. The...
Question 21: A human resources (HR) cost report was disclosed, by error, ...
Question 22: A project manager is managing an internal software developme...
Question 23: A company is transitioning from a predictive to an agile app...
Question 24: A large global organization developed a new medical implant ...
Question 25: A technical manager newly appointed by the client, visits th...
Question 26: The business manager and the product owner are requesting a ...
Question 27: Two key team members suggest different options to prevent ti...
Question 28: A project manager is managing a few innovation projects with...
Question 29: A project manager for a large multiyear industrial project h...
Question 30: A geographically distributed project team has development is...
Question 31: A project manager is working on a project that will transfor...
Question 32: A labor union contract negotiation is delaying the completio...
Question 33: A project manager has been assigned to deliver a challenging...
Question 34: A project manager analyzes the cumulative flow chart and ide...
Question 35: A senior project manager is working for a company that is no...
Question 36: A project manager is working on a cost-reimbursable contract...
Question 37: A customer calls the project manager to express concern abou...
Question 38: An important email from a project sponsor states that a back...
Question 39: A project manager has expertise in the technical domain. The...
Question 40: While monitoring a project at a work site, the project manag...
Question 41: A project manager and project team developing a new product ...
Question 42: A project manager is working with team members and customers...
Question 43: Due to a company merger and acquisition process, the main st...
Question 44: A project manager is working on a multinational project that...
Question 45: Anew law was published about zoning permits for telecom towe...
Question 46: A project manager was informed by their supplier that there ...
Question 47: One phase of a project took much longer than initially antic...
Question 48: A project manager is appointed to manage an infrastructure p...
Question 49: A project manager has taken over an existing project Accordi...
Question 50: In an agile project, two key stakeholders disagree about a m...
Question 51: In a weak matrix environment, two key team members are falli...
Question 52: A project manager is leading a large public project that wil...
Question 53: An IT project manager for a project that is 50% complete tea...
Question 54: A project needs to be outlined as a phased approach for mult...
Question 55: A project requires the installation of a call center to supp...
Question 56: A project manager is leading a project in which key performa...
Question 57: A project manager has recently moved to an organization to l...
Question 58: Due to unforeseen circumstances, a contractor was unable to ...
Question 59: As a result of the first iteration review, the stakeholders'...
Question 60: At a meeting to receive approval for the project management ...
Question 61: A project manager invites the company CEO, sponsor, team mem...
Question 62: Travel restrictions are suddenly imposed during a project's ...
Question 63: A project manager works in a startup company and is in charg...
Question 64: A technology project is delivering new functionality on a ne...
Question 65: At the end of a canceled project, the project manager sent s...
Question 66: Important projects in the portfolio backlog need to be deliv...
Question 67: During the execution of a project to develop a prototype, th...
Question 68: An organization is introducing agile to its projects. During...
Question 69: A project manager has been hired to help coordinate an ongoi...
Question 70: A self-organizing team for a critical project is consistentl...
Question 71: In an iteration-based marketing project, a product is schedu...
Question 72: A project manager leads a development project for a mobile c...
Question 73: To estimate the costs of a new project that is similar to a ...
Question 74: Some of the more experienced members of a project team have ...
Question 75: A new building project is in the middle of its life cycle. T...
Question 76: A protect manager has just finished planning for a project w...
Question 77: A project manager has been assigned to a project and receive...
Question 78: A business analyst on the project meets the customer in the ...
Question 79: A project engineer in country A is complaining about the sam...
Question 80: The project manager is having difficulty communicating with ...
Question 81: The product team is progressing with a prototyping approach ...
Question 82: A project team has been formed and the tasks have been assig...
Question 83: A project manager finds an unexpected issue halfway through ...
Question 84: A newly formed project team includes team members who have b...
Question 85: A project manager assigned to an engineering construction pr...
Question 86: A multimillion-dollar project has started and is in the exec...
Question 87: A project manager is managing a new development program to a...
Question 88: In a standup meeting a team member has been providing the sa...
Question 89: A project manager is leading a team of diverse individuals o...
Question 90: A project manager is assigned to an organizational transform...
Question 91: A company just started managing a project using an agile app...
Question 92: A project manager recently finished a project and started ma...
Question 93: A project being constructed in a remote rural area is nearin...
Question 94: A company is working on a project to develop an integration ...
Question 95: The project team follows a hybrid framework for its delivery...
Question 96: A research and development team is finishing up a two year i...
Question 97: Match the project situation on the left to the meeting on th...
Question 98: A project manager arranged a team-building activity to build...
Question 99: A new project manager is assigned to lead an agile project T...
Question 100: A project manager working on a large-scale network implement...
Question 101: A company has decided to implement a new archiving system A ...
Question 102: A project team member wants to select specific challenging t...
Question 103: A project manager is leading the first agile project for the...
Question 104: A project team was hired to perform on-site duties, but ther...
Question 105: A project manager determines that a critical path activity i...
Question 106: An organization has historically executed most projects usin...
Question 107: A team member has experienced personal conflicts on past pro...
Question 108: A project manager is beginning a new project with very diver...
Question 109: A project team consisting of various professionals of differ...
Question 110: A third-party supplier demands payment for the services prov...
Question 111: A project manager is asked to implement a hybrid approach th...
Question 112: A project manager is assigned to a project team midway throu...
Question 113: A healthcare organization hired a new compliance specialist ...
Question 114: A project manager is assigned to a multiyear enterprise reso...
Question 115: A team working on a close deployment waits to receive critic...
Question 116: A project manager is managing a large project. During a revi...
Question 117: During a team meeting the project manager asks the team to c...
Question 118: A project manager is instructed by the project sponsor to dr...
Question 119: In a project using a hybrid approach, the performance of the...
Question 120: A project manager is managing the development of a dental wi...
Question 121: An agile project team is tasked with a new project After mul...
Question 122: The project manager has recently received funding approval f...
Question 123: In the middle of a software development project, the lead de...
Question 124: When a project is in its final stage, the project manager wi...
Question 125: A project manager is working as a servant leader for a pilot...
Question 126: A company initiated a departmental transformation project im...
Question 127: A project manager is tasked with developing a coaching model...
Question 128: A business stakeholder for a project is reluctant to accept ...
Question 129: A project team has been working together for about 2 years. ...
Question 130: A project manager has a team of shared resources from other ...
Question 131: Drag the communication event on the left to the mam subject ...
Question 132: A project manager is managing an agile project for the first...
Question 133: A project manager is working to create a product that can be...
Question 134: A supplier is hired to provide information security services...
Question 135: A team is working on implementing a communications system wh...
Question 136: A project manager is assigned to a yearlong project. Before ...
Question 137: Team members are having a discussion with the project manage...
Question 138: A project team is executing a project to replace an existing...
Question 139: A project team is identifying project risks for a bridge to ...
Question 140: A proof of concept for a proposed solution was conducted dur...
Question 141: A project manager is working on a major construction project...
Question 142: During a meeting with a customer, it was determined that par...
Question 143: While developing a new product, a key stakeholder expresses ...
Question 144: A supplier informs the project manager that producing the qu...
Question 145: A retail company identifies that it is losing sales because ...
Question 146: During the forming phase of a project team a project manager...
Question 147: A project manager is struggling to figure out the performanc...
Question 148: An organization is about to start a multiphased project. Due...
Question 149: It is late at night on a weekend when a team member calls th...
Question 150: A few developers have submitted their resignation after comp...
Question 151: A credit collection company is implementing new software to ...
Question 152: After assigning tasks to a project team, a project manager d...
Question 153: Due to a statewide emergency, a project team for a global in...
Question 154: local company is developing a new product and. for the first...
Question 155: A project has a very tight delivery schedule The project is ...
Question 156: A business transformation project has a four-phase delivery ...
Question 157: During a retrospective, one of the team members reports that...
Question 158: During a daily standup meeting, a roadblock was raised that ...
Question 159: A company is launching a new product that has to be ready be...
Question 160: An agile project has a broad set of product features intende...
Question 161: A project team began working on a complex project that invol...
Question 162: A product company is transforming the way it develops and re...
Question 163: After signing an agreement with a vendor, the project manage...
Question 164: A project has a very tight delivery schedule. The project is...
Question 165: A project manager works for an organization that intends to ...
Question 166: During daily calls team members share task progress One team...
Question 167: A project manager is using an agile approach. During the spr...
Question 168: A project manager is leading a meeting with key stakeholders...
Question 169: A company has started developing a new product. During execu...
Question 170: A company is leading a project to develop a new product usin...
Question 171: A telecommunications project consists of departments spread ...
Question 172: A key import supply has suffered a delay of 6 months. The de...
Question 173: A customer requests additional changes 1 day before the plan...
Question 174: A risk was identified at the beginning of a project, and a r...
Question 175: A new resource has joined an iterative project team The proj...
Question 176: A customer asks the project manager about opportunities to c...
Question 177: A project team is planning the next sprint review. The proje...
Question 178: A project manager is working in a company that has several g...
Question 179: During project execution, the risk owner is monitoring the c...
Question 180: A project manager holds periodic progress review meetings to...
Question 181: A prefeasibility study for a new renewable energy project is...
Question 182: At the end of a project, the project manager is asked to sub...
Question 183: A multinational company has a plan to expand their business ...
Question 184: A project manager is leading a global team that they have wo...
Question 185: A company's leadership team has decided to invest in a new p...
Question 186: A consultancy firm is finally selected and contracted for a ...
Question 187: A project manager is working on the implementation of new ph...
Question 188: An organization imports many of the materials for a product ...
Question 189: During an ongoing project a key resource asks the project ma...
Question 190: A project manager for a large software delivery project is i...
Question 191: On a project to create the perfect paper airplane, the devel...
Question 192: An agile project manager has learn members from different co...
Question 193: A project manager is assigned to deliver a development proje...
Question 194: A project scope was developed with numerous assumptions. Dur...
Question 195: A project manager for a digital transformation project has a...
Question 196: A project manager is assigned to an automotive product devel...
Question 197: Several components of an expensive manufacturing project hav...
Question 198: Drag the characteristics of the stage on the left to the cor...
Question 199: In a financial company, a strategic project has been planned...
Question 200: A project manager resigned from a recently approved project....
Question 201: A project is 70% complete when the project sponsor requests ...
Question 202: The project sponsor on an agile project informed the project...
Question 203: A project manager is assigned to a global project with dispe...
Question 204: A project manager scheduled a session to identify risks on t...
Question 205: A project manager is managing a very important business tran...
Question 206: A project manager noticed that the functional manager is not...
Question 207: A project manager has been assigned to lead an IT project to...
Question 208: An agile project to provide a material information system ha...
Question 209: A team is having a hard time completing work due to unclear ...
Question 210: A retail chain is evaluating a project to replace payment sy...
Question 211: A Scrum team is analyzing the burndown chart on day four of ...
Question 212: A project manager /s planning a project and identifies that ...
Question 213: A project manager is newly appointed to lead a project team ...
Question 214: A project manager is building a team to work on a service in...
Question 215: A subcontracting company is presenting its feature release A...
Question 216: A project manager is worried that a key stakeholder is not p...
Question 217: During the daily meetings with the team the project manager ...
Question 218: A project manager is managing an agile project that is part ...
Question 219: The project management office (PMO) assigns a project manage...
Question 220: A client wants to create an innovative software for the trav...
Question 221: A project manager led the implementation of an electronic in...
Question 222: Due to a tight schedule, a project team member suggests skip...
Question 223: A project manager is leading a progress review meeting when ...
Question 224: During a project to develop a new pharmaceutical product, th...
Question 225: A project manager wants to make sure that similar projects i...
Question 226: A project manager is working with an agile team to enhance a...
Question 227: A verbal announcement is made that the new team member joini...
Question 228: A project manager submits a version of the software that the...
Question 229: A project manager has been assigned to a project that is in ...
Question 230: The project team finds that the latest delivery from a vendo...
Question 231: A large and complex program in an agile environment has expe...
Question 232: Early in a project, a team member failed to effectively comm...
Question 233: When a project manager is trying to determine a leadership s...
Question 234: During project planning, a development team is assigned an a...
Question 235: An agile team has completed five sprints. The final product ...
Question 236: A project manager has been approached by the project sponsor...
Question 237: An agile team is conducting a sprint retrospective and wants...
Question 238: The team is working on a critical project deliverable and th...
Question 239: A project manager leads a software development project in a ...
Question 240: A project team has been together for a long time and has bee...
Question 241: The programming activities of a project were planned to last...
Question 242: A new project manager is planning an information security pr...
Question 243: A company's project management office (PMO) has been trying ...
Question 244: As a project is reaching completion, the project sponsor tel...
Question 245: A project is scheduled to end in 2 weeks. The team is expect...
Question 246: A project stakeholder has expressed concern that the establi...
Question 247: A project team member complained to the project manager that...
Question 248: A project manager working on a software development project ...
Question 249: A project manager is working on the delivery of a solution t...
Question 250: An agile team is brainstorming and prioritizing all of the r...
Question 251: A project manager identifies an issue between two team membe...
Question 252: In an agile project, the learn planned to complete 40 story ...
Question 253: How can agile measurements improve upon predictive measureme...
Question 254: After a performance review, a team member approaches the pro...
Question 255: A project manager who is managing a critical project in a mu...
Question 256: A company is implementing a project with team members locate...
Question 257: A client comes to the company asking to copy a project that ...
Question 258: A project manager is leading a strategic and competitive adv...
Question 259: A project manager works for a large manufacturing company wi...
Question 260: A team is delivering features to a customer at every iterati...
Question 261: A client is structured as a matrix organization for an agile...
Question 262: During the development of a product, multiple identified ris...
Question 263: A company that is introducing a new product into the market ...
Question 264: A project team is implementing a hosted system for a third p...
Question 265: A company is using an agile approach to launch a new product...
Question 266: A project manager identifies a risk that has a high probabil...
Question 267: After a project team has been working on a project for sever...
Question 268: During a project meeting, the project manager asks risk owne...
Question 269: A laboratory is launching a new product, defined to be execu...
Question 270: When defining the ground rules for a project team, the proje...
Question 271: A project manager is leading a hybrid project. The self-orga...
Question 272: A team is working on a hybrid project. Due to different inte...
Question 273: During the execution of a construction project, the project ...
Question 274: Throughout an entire project, the project manager took notes...
Question 275: A project manager is working on a project to build a manufac...
Question 276: The project manager of a high-risk project is concerned abou...
Question 277: A project manager is attending a progress meeting with a cli...
Question 278: A project leader is assigned to a new project and is asked t...
Question 279: A supplier, who was tasked with providing an important compo...
Question 280: A project manager has been assigned to a long-term project. ...
Question 281: An agile project for a database migration impacts nearly all...
Question 282: A project manager finds it challenging to comply with standa...
Question 283: A company made several changes recently, which resulted in a...
Question 284: A project manager is implementing an enterprise-wide softwar...
Question 285: A team has been working on a project for several months,, bu...
Question 286: A high-tech borehole protect was initiated with the goal of ...
Question 287: A new project manager is assigned to a project in the execut...
Question 288: A project manager is a part of the project management office...
Question 289: A company is developing a new product. During project planni...
Question 290: Some members of a project team are frustrated by a new team ...
Question 291: A project manager has been working with the same group of st...
Question 292: Which three of the following scenarios are impediments to wh...
Question 293: A new team member joins an agile team. In a previous role, t...
Question 294: A team member misses a project meeting without it being appr...
Question 295: A team needs to follow defined cybersecurity compliance that...
Question 296: A company has a transformation project in progress. During a...
Question 297: A project manager wants to assign a junior engineer to a new...
Question 298: A project manager has joined a company m an unfamiliar indus...
Question 299: During project execution, a project manager is informed that...
Question 300: A key team member shared confidential information about anot...
Question 301: A project manager is managing a technical project that requi...
Question 302: A project manage is in the middle of an angle project compri...
Question 303: A project manager is working on a complex project with a hig...
Question 304: A project manager is leading a project to modemize the infor...
Question 305: A project manager leads a project that implements a new proc...
Question 306: Within a project, senior management is requesting project in...
Question 307: A project is coming to a close, and the experienced project ...
Question 308: A project manager is assigned to a technical research projec...
Question 309: A project team member informs the project manager that a sta...
Question 310: In a project, one core team member tends to do all the work ...
Question 311: In the middle of a project, a business unit manager who regu...
Question 312: In the middle of an iteration, the product owner tells the a...
Question 313: A project team is executing a megaproject, and several contr...
Question 314: A project for Company A was successfully delivered within sc...
Question 315: A project manager is assigned to a project to develop a mobi...
Question 316: A project manager submits several requests to purchase requi...
Question 317: A project manager is appointed for the deployment of a new s...
Question 318: A company's project management office (PMO) is incorporating...
Question 319: During the third iteration of a project, the main sponsor re...
Question 320: A company is transitioning projects from a predictive to an ...
Question 321: A project is being executed The project's life cycle is defi...
Question 322: A customer initiated a minor scope change and expects this t...
Question 323: A project manager is responsible for providing a budget esti...
Question 324: During a project's planning session, the project team discus...
Question 325: A project manager is closing a project and preparing to hand...
Question 326: A large company has agreed on a business case for an environ...
Question 327: In a hybrid project, 100 new base stations are being added t...
Question 328: A project manager is reviewing the lessons learned for an hi...
Question 329: A project manager is assigned to a project that is in the ex...
Question 330: A business improvement opportunity to reduce energy usage ha...
Question 331: A project manager notices that the project team is unlikely ...
Question 332: In an agile team, some of the team members are coming forwar...
Question 333: A team is currently working on a mobile app solution. During...
Question 334: A company has agreed to run a transformation project using a...
Question 335: During a project, the project manager finds an opportunity t...
Question 336: An internal virtual team is meeting daily to review iteratio...
Question 337: A junior project manager is excited to start working on thei...
Question 338: A hybrid project manager has taken over a large-scale softwa...
Question 339: A team is given an agile project to build a conceptual produ...
Question 340: A company's board of directors announced that a major layoff...
Question 341: A project manager is managing a complex research project wit...
Question 342: For the purposes of quality assurance a quality audit was co...
Question 343: The change control board (CCB) rejects a change request subm...
Question 344: A project manager acquired information from the market that ...
Question 345: A project manager is leading a project in an organization th...
Question 346: (Exhibit) According to this burnup chart for the last 7-day ...
Question 347: A project manager realizes that a project is becoming delaye...
Question 348: One of the team members is always late to the daily standup ...
Question 349: From previous lessons learned working with a client, a proje...
Question 350: A project manager is leading a project that is on time and u...
Question 351: A customer interacts directly with a Scrum team and continua...
Question 352: A project team has installed software for the client, passed...
Question 353: After gathering all the requirements for a project with depe...
Question 354: A company's CEO has just returned from a conference on the u...
Question 355: A Scrum team has committed to delivering a specific capabili...
Question 356: A project manager is leading a product feature rollout that ...
Question 357: A project sponsor asks the project team to add an enhancemen...
Question 358: An agile project will be delivered to a client based on a fi...
Question 359: During a retrospective meeting a project manager hears that ...
Question 360: An organization embarking on a significant transformation in...
Question 361: A developer who has almost completed a required product feat...
Question 362: A hybrid project team is working on an upgraded version of s...
Question 363: A project is on its sixth iteration out of seven. Select the...
Question 364: A key project stakeholder who was a big supporter and motiva...
Question 365: A project manager is assigned to lead a newly formed agile t...
Question 366: A project manager has just taken over a project that is half...
Question 367: A product owner presented the backlog to the team, and the t...
Question 368: After reviewing the lessons learned database, a project mana...
Question 369: A major issue about conflicting priorities has been highligh...
Question 370: Two teams are engaged on a global project which uses a follo...
Question 371: A key project stakeholder has started to escalate all issues...
Question 372: A project manager noticed that the functional manager is not...
Question 373: During the executing phase, a project manager is reviewing t...
Question 374: An agile team is working on a 2-week sprint to deliver busin...
Question 375: A product owner is invited to a sprint review meeting. At th...
Question 376: A project is on its fourth iteration out of six. During iter...
Question 377: An organization's management system is being upgraded by an ...
Question 378: A project manager has recently joined a small company. The c...
Question 379: A junior project manager was recently hired to lead a comple...
Question 380: A project manager has been assigned to a project that involv...
Question 381: A project manager has heard about the large volume of emails...
Question 382: An integrated project involves the interaction of both hardw...
Question 383: A recently concluded quality audit failed and came back with...
Question 384: A project manager is leading a project to develop accounting...
Question 385: A project manager just completed a successful deployment and...
Question 386: A project manager has been assigned to a hybrid project that...
Question 387: During the last two iterations of a project, one of the team...
Question 388: A project manager is managing a project with a hybrid approa...
Question 389: An organization is undergoing an agile transformation. The e...
Question 390: A project manager is leading a project that is in the execut...
Question 391: A project manager is managing two agile teams and reviewing ...
Question 392: A project manager is asked to develop maintenance planning s...
Question 393: A team shared a complaint regarding the scrum master during ...
Question 394: A project manager is leading a project that involves on-site...
Question 395: A learn member has a sudden emergency that may last for seve...
Question 396: At the end of the last iteration, the customer rejects the d...
Question 397: A junior team member escalates an issue to the project manag...
Question 398: Two weeks after the approval of the project management plan ...
Question 399: A project manager is managing the transition to operations. ...
Question 400: A project manager is leading a product development project t...
Question 401: A project team has recently finished a sprint for developing...
Question 402: A healthcare company requires all new employees to attend ma...
Question 403: A project manager is leading three projects in a program foc...
Question 404: A project manager for a maintenance project has a contract t...
Question 405: At a project meeting, a business analyst requires input from...
Question 406: A project manager is working with an agile team. A key stake...
Question 407: A company just started managing a project using an agile app...
Question 408: While finalizing project management plans, a customer provid...
Question 409: A hybrid project has just deployed, and the project manager ...
Question 410: A company has assigned a project manager to the initial task...
Question 411: During the release of an important product, a vice president...
Question 412: In a construction project for a new building, the project ma...
Question 413: During the design phase of a project the project manager not...
Question 414: During protect execution the project manager observes lower ...
Question 415: A few key stakeholders are concerned about how the prefect t...
Question 416: A project manager is assigned to a strategic communication p...
Question 417: A project manager finds that there are knowledge gaps in the...
Question 418: A new team member is assigned to a team that consistently de...
Question 419: A multinational company is launching a company-wide digital ...
Question 420: During an inspection, the production phase was stopped becau...
Question 421: An agile leader is working on a complex project that is ente...
Question 422: A project is halfway through its execution phase. The qualit...
Question 423: A project manager is implementing a new software system Some...
Question 424: Anew systems project requires feedback from the accounting m...
Question 425: During the early phase of a project, the requirements docume...
Question 426: A customer's technical lead discussed a new feature with the...
Question 427: A company is conducting a digital transformation project tha...
Question 428: At the end of a project's initiation phase, the budget was d...
Question 429: A project manager has just been assigned to a team that is d...
Question 430: A project learn member identified a defect in the initial so...
Question 431: An issue reoccurs six months after a project's go-live date ...
Question 432: A project team is engaging a development team in another cou...
Question 433: A project manager is new to hybrid project management and is...
Question 434: A project manager is assigned to a new marketing campaign Th...
Question 435: A key project stakeholder showed interest in the beginning o...
Question 436: The product backlog has been completed and prioritized. and ...
Question 437: A new marketing vice president just joined a software startu...
Question 438: A new project manager has been assigned to a project that is...
Question 439: A project manager is leading a project that needs to be depl...
Question 440: Project stakeholders are engaged in a discussion on how to a...
Question 441: A member of a testing team in an agile project works well wi...
Question 442: A project manager is working on the budget for a long-term p...
Question 443: A project manager is leading a project when a key stakeholde...
Question 444: During the execution stage, the project manager discovered t...
Question 445: A Scrum team is analyzing the burndown chart on day four of ...
Question 446: A project manager has just received communication from an op...
Question 447: A project manager has been managing an agile project for 6 m...
Question 448: A project team member raised a risk that the threat of count...
Question 449: After a meeting with the customer, the project manager recei...
Question 450: A new development project is about to start, and the project...
Question 451: An organization is transitioning to agile. The project manag...
Question 452: An agile project team received an assignment to develop an i...
Question 453: The team architect resigned from the company. The new archit...
Question 454: A project manager is tasked with large deliverables that req...
Question 455: One of the service providers on a complex project has been f...
Question 456: On a recently completed prefect a project manager noticed th...
Question 457: A project is ending its fifth out of six iterations. During ...
Question 458: During the execution phase of a healthcare IT project, the p...
Question 459: A company is implementing a new system The project manager h...
Question 460: A project to implement a new online landing platform has sta...
Question 461: A construction services company has influence within the loc...
Question 462: A company has transitioned and is now delivering projects us...
Question 463: A project manager receives information in preparation for re...
Question 464: In an ongoing project, stakeholders have been approaching te...
Question 465: A senior management team member contacts an agile project le...
Question 466: A project manager had to schedule additional planning sessio...
Question 467: The customer wants to show their stakeholders a tangible out...
Question 468: An insurance company is planning to make a big change to its...
Question 469: A project using a hybrid approach to migrate from a current ...
Question 470: Project A is critical for the company and must be completed ...
Question 471: A project team has transitioned to full-time remote working....
Question 472: An organization is embarking on the deployment of a new digi...
Question 473: An agile team was hired to work on a public service project....
Question 474: During a status review meeting a team member raises concerns...
Question 475: The project manager is reviewing a project's progress and no...
Question 476: During the course of a project, the project manager wants to...
Question 477: A stakeholder is requesting that the project manager share p...
Question 478: In an attempt to streamline project communications, a projec...
Question 479: A project manager is part of a balanced matrix project organ...
Question 480: A team is the first team m the company to use agile methods ...
Question 481: A project was initiated due to an external business influenc...
Question 482: During an agile team retrospective, a project team member me...
Question 483: A stakeholder on a project has a reputation for being easily...
Question 484: A project manager has been given a critical, 5-day window an...
Question 485: An agile team completes a deliverable that is to be certifie...
Question 486: A project manager is overseeing a project as part of a progr...
Question 487: An agile coach and technical writer for a globally distribut...
Question 488: A team is ready to start working on a project with a custome...
Question 489: While following up on a deliverable, a team member expresses...
Question 490: A senior manager attends one of the project review meetings ...
Question 491: Drag the items on left side to the matching term within the ...
Question 492: During the course of a project the project manager's immedia...
Question 493: Key decision makers are meeting to define the objectives of ...
Question 494: A project is ending its fifth out of six iterations. During ...
Question 495: A large multi-year project requires highly skilled staff for...
Question 496: A company is about to start a complex research project. Due ...
Question 497: A project manager is managing a large project. A stakeholder...
Question 498: A project manager is leading a multiyear project that involv...
Question 499: A project manager is leading an integration project for a re...
Question 500: A project manager receives a request for proposal (RFP) from...
Question 501: A company recently adopted agile to develop innovation proje...
Question 502: The operations director complains to the CEO about the outco...
Question 503: After a couple of iterations the project manager decides to ...
Question 504: After sending an on-site meeting invitation to seven people ...
Question 505: A protect manager is struggling to obtain participation from...
Question 506: The project manager realizes that the product owner has a lo...
Question 507: A team is working on a project using a hybrid approach, and ...
Question 508: A new project manager is assigned to a project that will del...
Question 509: A project manager is working on a financial system implement...
Question 510: An experienced project manager is overseeing a merger and ac...
Question 511: A project manager is assigned to a hybrid project involving ...
Question 512: During a product demo with key stakeholders, the team identi...
Question 513: A project manager notices that the team lacks a subject matt...
Question 514: A product owner has an idea for a new product but is struggl...
Question 515: An agile project manager notices that one of the team member...
Question 516: A protect is going through its iterative design stage One of...
Question 517: A project manager has recently been assigned to an agile pro...
Question 518: One of the main inputs required for a deliverable is missing...
Question 519: A project manager has noticed that a critical team member is...
Question 520: A project manager must manage a virtual application control ...
Question 521: A project team is working on an agile software development p...
Question 522: An information technology (IT) team is responsible for the v...
Question 523: During project implementation, one team finds out that a key...
Question 524: During the setup of an agile project, the product owner expr...
Question 525: A project manager has been assigned to an important project ...
Question 526: A customer wants to launch a new product in the market and a...
Question 527: A project to develop a large hydropower plant is in the impl...
Question 528: During the execution of a construction project, one of the n...
Question 529: A project manager is working on an enterprise resource plann...
Question 530: During a kick-off meeting, the project manager notices that ...
Question 531: A team needs to implement a mandatory compliance regulation ...
Question 532: In a geographically distributed project team, the project te...
Question 533: A project manager just started managing agile projects The p...
Question 534: A project manager Is leading an agile software development p...
Question 535: A project manager is preparing a project closure report. The...
Question 536: The project sponsor of a major initiative is consistently ch...
Question 537: A project is nearing completion The contingency time has bee...
Question 538: A customer is meeting with an agile team at regular interval...
Question 539: A supplier was supposed to mobilize a government-issued, lic...
Question 540: The current incremental revenue expected by a project delive...
Question 541: A project manager at a large corporation has been assigned t...
Question 542: A project team member was unhappy with a new change in proje...
Question 543: A project manager has been managing a project for several mo...
Question 544: In the middle of an iteration a team member suggests a new m...
Question 545: A project manager is acting as a scrum master in a hybrid pr...
Question 546: The project velocity has recently slipped, and a decision wa...
Question 547: An organization uses a predictive approach but is open to us...
Question 548: An agile team is geographically separated across multiple co...
Question 549: Knowledge sharing has been a key priority for a complex tech...
Question 550: An agile project team is working on an infrastructure produc...
Question 551: A sponsor and project manager found out that a vendor in a d...
Question 552: A project manager is working on a project with multiple work...
Question 553: During a project review meeting, several project team member...
Question 554: During the implementation of a project the project team disc...
Question 555: A project manager is in the middle of an agile project compr...
Question 556: Due to a recent budget reduction, two team members were rele...
Question 557: A project team member does not submit the project status rep...
Question 558: The project manager is reviewing the program risks and issue...
Question 559: A project manager is assigned to an agile project that has a...
Question 560: A project for a new product launch is in a very initial stag...
Question 561: Toward the end of a protect the project manager did not rece...
Question 562: A team has developed and tested new software to control airp...
Question 563: A project manager is working with several junior engineers o...
Question 564: A company wants to increase the commercial value of one of i...
Question 565: A project manager who recently joined the company has been a...
Question 566: A company's new communication system will include online das...
Question 567: During the last sprint review the product owner stated that ...
Question 568: Contract terms used during the tender phase for a new power-...
Question 569: A company is working on a project and is using a hybrid appr...
Question 570: During the execution phase, the project manager discovered t...
Question 571: A project manager notices that the response action for an id...
Question 572: A year after implementing a policy change to improve diversi...
Question 573: During the planning stage of a project the project manager r...
Question 574: A project manager has just completed a fixed-price project a...
Question 575: A Scrum team working in an aircraft manufacturing company ha...
Question 576: One team member is not as active as the rest of the team dur...
Question 577: A project to implement a new process is still in development...
Question 578: A project manager is part of a distributed team. The project...
Question 579: A company has undertaken a large transformation project in p...
Question 580: An experienced project manager is leading an enthusiastic te...
Question 581: During a project planning phase, the project manager realize...
Question 582: After conducting a performance assessment, the project manag...
Question 583: A new team member has joined an agile project, replacing a t...
Question 584: A project manager schedules virtual daily standup meetings f...
Question 585: A software system is being built for a company. Once the sys...
Question 586: A project manager is leading a project with a predictive app...
Question 587: After reviewing the project management plan with key stakeho...
Question 588: For an ongoing project, match the key performance indicators...
Question 589: During a project's initiation phase a lessons learned sharin...
Question 590: An organization has recently decided to switch from a predic...
Question 591: While managing a project using a hybrid approach, the projec...
Question 592: A team member has indicated their user story will not be fin...
Question 593: A procurement team lead has been reported as getting into co...
Question 594: An agile team is making infrastructure changes to the human ...
Question 595: An external project manager is managing the construction of ...
Question 596: A new relevant project stakeholder suggested a change to som...
Question 597: In a time-critical construction project, a misunderstanding ...
Question 598: A project manager is managing the opening of a new office ov...
Question 599: A multiyear resource constraint project is midway through th...
Question 600: The marketing team is transitioning to using hybrid approach...
Question 601: In a multinational project, stakeholders are in different ti...
Question 602: A protect team member is having difficulty delivering assign...
Question 603: A project manager is leading a software development project ...
Question 604: A new project manager is managing a hybrid project. The proj...
Question 605: An organization uses a hybrid approach to project management...
Question 606: A project manager is newly appointed to an ongoing project t...
Question 607: During a regular project progress meeting, the CEO informed ...
Question 608: project manager for a defense software application has a cul...
Question 609: A project manager is managing an internal project that was p...
Question 610: A complex project is in the execution phase. A key stakehold...
Question 611: A technician is scheduled to install internet service at the...
Question 612: A project manager is in rapid development mode on a joint ap...
Question 613: A project's customer is furious. When the customer arrived a...
Question 614: DRAG DROP Drag the interpersonal skill on the left to the co...
Question 615: A learn has been working for two months and has consistently...
Question 616: During the review of a project's list of deliverables, one o...
Question 617: A bank is considering building another branch in one of thre...
Question 618: Five agile teams working together on a product recently perf...
Question 619: A vendor project manager and team are implementing a softwar...
Question 620: In a geographically distributed team, a developer continues ...
Question 621: A project manager is assigned to a dental equipment developm...
Question 622: After the project charter's approval the project manager nee...
Question 623: After reviewing the project management plan with key stakeho...
Question 624: A project manager is assigned to a new project. The project ...
Question 625: During a retrospective review, many project team members say...
Question 626: A project manager is part of a team that is launching a seri...
Question 627: A project manager has been assigned to take over an existing...
Question 628: A project team member reads in a financial newspaper that th...
Question 629: A project to build a new energy plant was just completed. Ho...
Question 630: A project is about to start. The project manager has found t...
Question 631: There is frequent conflict between two project team members ...
Question 632: A project manager is assigned to deliver an innovative solut...
Question 633: According to the project contract the delivery date is appro...
Question 634: A company is initiating a project to decommission inefficien...
Question 635: A feature has been added to the iteration backlog that has b...
Question 636: A major national company known for quality products has just...
Question 637: An organization is transitioning to an agile environment. Th...
Question 638: A project leader of an agile team realizes that one team mem...
Question 639: An important national project is in (he execution phase. A t...
Question 640: A project is almost completed, and both the sponsor and the ...
Question 641: During project execution, a conflict occurs between the proj...
Question 642: A key resource is newly assigned to a project. The project m...
Question 643: According to a new product development process, the marketin...
Question 644: Halfway through a project, the project sponsor is replaced b...
Question 645: A project manager is leading a large-scale project that invo...
Question 646: A project is ready to start, and resources are allocated. Th...
Question 647: Which two actions should a project manager consider while la...
Question 648: A project team is transitioning from a predictive to an agil...
Question 649: A company was awarded a project in a dangerous location that...
Question 650: The scope of a project is to replace the street signs within...
Question 651: During a project meeting, the project manager expressed the ...
Question 652: A project manager is transferred to another country to perfo...
Question 653: In a global project, the project manager has to plan and man...
Question 654: A project team is working on the design of a solution for a ...
Question 655: During the execution phase of a project, a project manager n...
Question 656: A project manager is assigned to a building construction pro...
Question 657: A project involves exporting 150 packages to the customer. H...
Question 658: A few virtual team members are located in a region that gene...
Question 659: A company changed the product owner on an existing project. ...
Question 660: An organization is transitioning to agile and a project has ...
Question 661: An enthusiastic, newly hired vice-president has been assigne...
Question 662: A project manager is tasked with managing a customer relatio...
Question 663: A team member has encountered a technical issue similar to t...
Question 664: A project manager was recently assigned to rescue a high-pri...
Question 665: A company that uses a predictive approach and operates in a ...
Question 666: A mandatory compliance requirement that will impact the proj...
Question 667: A team member has very strong technical skills and is intere...
Question 668: A project manager works at an organization that intends to u...
Question 669: During a kick-off meeting at the start of project execution,...
Question 670: A project manager has been managing a highly complex project...
Question 671: A project manager is appointed for the deployment of a new s...
Question 672: A project that is using an incremental approach has colocate...
Question 673: During a project's execution phase, two team members are hav...
Question 674: The project manager of a large construction project discover...
Question 675: A project manager is leading a software development project....
Question 676: After 1 year Into the life cycle of an ongoing residential p...
Question 677: A project manager encounters a governance issue during the p...
Question 678: A project manager is working on a construction project. The ...
Question 679: During project execution, an important stakeholder threatens...
Question 680: A junior project manager with experience in predictive proje...
Question 681: A project manager is assigned to a project that is in develo...
Question 682: A project is being delayed due to a large amount of rework c...
Question 683: A project manager learns from a marketing analyst that a com...
Question 684: A project, which has its execution phase planned m an iterat...
Question 685: A project team has developed the initial schedule using a ne...
Question 686: A project is on its fifth iteration out of six. One member o...
Question 687: During the third iteration of a project, the product owner r...
Question 688: An agile team has completed an iteration and delivered the a...
Question 689: A project manager is managing a project which has a very com...
Question 690: A project manager and project team have brought a project ba...
Question 691: A company has an existing contract to maintain and enhance a...
Question 692: A project manager has team members around the world in many ...
Question 693: During iteration two of a project with two teams {A and B), ...
Question 694: A company is running a project to eliminate a sales channel ...
Question 695: A project manager is managing a hybrid project After attendi...
Question 696: A project manager has received an updated earned value analy...
Question 697: A new team member on a self-organizing team is finding it di...
Question 698: A project manager for a software technology project works in...
Question 699: A company has created a cross-functional team to drive the d...
Question 700: A project manager is managing a project with team members wh...
Question 701: A project manager is working toward a deadline to prepare a ...
Question 702: A project manager is managing a megaproject. The project sta...
Question 703: A project manager at a company is considering a high-perform...
Question 704: At a meeting, the project manager for an agile project indic...
Question 705: A project manager is leading a hybrid project. The work brea...
Question 706: Just as a team reaches a mutual consensus on a preferred des...
Question 707: A project manager finds that team members In an agile projec...
Question 708: A company must implement a new regulation. The government ha...
Question 709: A project manager is working on a highly complex project. Du...
Question 710: A company is planning a digitization project. Which action s...
Question 711: Since the beginning of a project, the product owner keeps as...
Question 712: A few new team members working on a public housing project a...
Question 713: A hospital is running a project for one of their internal cr...
Question 714: A hybrid project is experiencing several issues with both th...
Question 715: A project manager is assigned to an ongoing complex project....
Question 716: A sales team working on an IT deployment project approached ...
Question 717: A key stakeholder is upset because the final product deliver...
Question 718: In a hybrid project, the customer decided on a major change ...
Question 719: A project manager manages multiple information technology (I...
Question 720: The project manager has observed that two team members have ...
Question 721: A project manager is working on a project with three virtual...
Question 722: A team is developing an experimental program to be used by t...
Question 723: A project manager just finished a meeting to identify the ma...
Question 724: A project manager who is experienced in predictive and adapt...
Question 725: A compliance strategy was created during the planning phase ...
Question 726: A key stakeholder is refusing to participate in a crucial pr...
Question 727: A project manager writes to the receiving organization to in...
Question 728: A team has been working for some time on a project with incr...
Question 729: A project is approaching its project closure phase, and the ...
Question 730: During the first project meeting with a new project manager,...
Question 731: During initiation of a new product improvement project, a pr...
Question 732: A new team member is hired and the training is taking longer...
Question 733: A new regulation has been approved that will impact the deli...
Question 734: A project manager is leading a project which shows a trend t...
Question 735: A team realizes that there is no access to data that the pro...
Question 736: During the design phase, a project manager realizes that the...
Question 737: During the execution phase of a project, a new department ha...
Question 738: A project manager has two projects that are being executed a...
Question 739: An agile project is in its early iterations, but the project...
Question 740: A project manager is managing a national rollout for an inno...
Question 741: A project manager has been assigned to a new project that is...
Question 742: A project manager is in the process of closing out a project...
Question 743: A project manager is working on a software development proje...
Question 744: A project manager notices that a new junior team member's su...
Question 745: A project manager is managing an innovation project for a bi...
Question 746: A project manager is assigned midway through a project. The ...
Question 747: A project started 12 months ago and is currently on iteratio...
Question 748: The project manager of an agile project has been asked to re...
Question 749: A product owner Goes not regularly attend demonstration cere...
Question 750: The project charter was just approved and the project sponso...
Question 751: A vendor has manufactured a complex product. During a factor...
Question 752: An agile team completes a deliverable that is to be certifie...
Question 753: A project manager is assigned to a new project that will lau...
Question 754: A team averages 100 story points per iteration. The team est...
Question 755: In a multinational multi location project with virtual teams...
Question 756: A project manager receives feedback from the customer's lead...
Question 757: A new team member is added to a self-organizing team. The ne...
Question 758: The project leader for an agile team has discovered that a c...
Question 759: During the initiation stage of a multimedia exhibition-desig...
Question 760: An international client contacted a software development com...
Question 761: A project manager has been moved to a new division and is in...
Question 762: A project has been running for 2 months and now requires app...
Question 763: A project manager is assigned to work on a large global proj...
Question 764: A project team is performing extremely well when it comes to...
Question 765: A project team needs to follow regulatory compliance guideli...
Question 766: A project is about to close and the project manager is p Set...
Question 767: A project manager is managing a project that is going to del...
Question 768: While working on a poorly defined internal project, a projec...
Question 769: A project team is having difficulties understanding technica...
Question 770: An agile leader notices that one team member consistently fa...
Question 771: The project is delayed due to the high amount of major chang...
Question 772: An agile team has been struggling to keep up with the planne...
Question 773: A town wants to build a community center and has appointed a...
Question 774: The project manager just started leading a project team from...
Question 775: A project manager is assigned to a multiyear project. During...
Question 776: In the planning phase, a project manager receives identified...