A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
Correct Answer: D
On day four of a 15-day sprint, the team should continue with the sprint work as planned and keep monitoring the burndown chart. The burndown chart is a visual representation of the work left versus the time remaining in the sprint. If the "Actual" line closely follows the "Planned" line, it indicates that the team is on track. Making adjustments or changing the sprint scope at this stage is premature unless there are significant deviations or impediments1. The team should maintain their current pace and monitor progress, making adjustments only if necessary as the sprint progresses2. References: "Burndown Chart: What it is, How to Use it, Example [2024]" by Asana; "Scrum Sprint Burndown Chart [Everything you Need to Know]" by KnowledgeHut12.