A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently. How should the project manager respond'?
Correct Answer: B
A hybrid project management methodology is a combination of two or more different approaches to delivering projects, such as waterfall and agile1. Hybrid projects can offer benefits such as flexibility, adaptability, customer satisfaction, and innovation2. However, hybrid projects also require frequent reviews and feedback loops to ensure alignment, collaboration, and quality among the project team and stakeholders3. Therefore, the project manager should explain to the stakeholder the value of attending the iteration reviews, which are opportunities to inspect the project deliverables, provide feedback, identify issues, and plan for the next iteration4. By doing so, the project manager can demonstrate how the stakeholder's involvement can contribute to the project success and avoid potential rework or waste. References: * Ultimate Guide To Hybrid Project Methodologies & How To Make Them * Hybrid project management - the key to a successful future? - APM * Hybrid project management - a systematic literature review ... * TOWARDS A HYBRID PROJECT MANAGEMENT FRAMEWORK: A SYSTEMATIC LITERATURE ...