During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?
Correct Answer: B
In project management, it is crucial to manage dependencies effectively to ensure that critical activities are completed on time. The project manager should ensure that team B prioritizes the dependent activity in iteration three to align with the schedule of team A's critical activities set for iteration four1. This approach is supported by best practices in managing project dependencies and inter-team coordination, ensuring that all necessary tasks are accounted for and scheduled appropriately23. References: * PMI's Guide to the Project Management Body of Knowledge (PMBOKGuide)4. * Professional in Business Analysis Reference Materials5. * Best practices in managing project dependencies23. * Discussions on PMP exam topics related to managing dependent activities between teams1