A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria defined by the product owner and does not understand what went wrong. How should the project manager mitigate the product rejection?
Correct Answer: B
Engaging the main stakeholders in the sprint review sessions is a key agile practice to ensure continuous collaboration and feedback. It allows stakeholders to provide input and clarifications, ensuring that the product evolves to meet their needs and expectations. This approach aligns with the agile principle of customer collaboration over contract negotiation and promotes transparency and adaptability. References: = The PMI Guide to Business Analysis1, which includes The Standard for Business Analysis, and the PMBOKGuide2 both emphasize the importance of stakeholder engagement and collaboration throughout the project lifecycle.