An agile project is in its early iterations, but the project manager already realizes that more resources will be needed to achieve the expected time lines. There are no internal resources. available. What vendor strategy should the project manager use to maximize project delivery?
Correct Answer: C
In an agile project, especially in its early iterations, flexibility and adaptability are key. When more resources are needed and there are no internal resources available, the project manager should engage in a time and materials (T&M) contract and hire a local vendor to support development1. This approach allows for greater flexibility as the project evolves and changes, which is a hallmark of agile projects2. It also allows the project manager to bring in expertise as needed, without committing to a fixed scope or price3. This strategy maximizes project delivery by ensuring that the necessary resources are available when needed, while also maintaining the flexibility inherent in agile projects123. References: PMI Vendor Management Strategies, PMI Vendor Management Practices, Gartner