A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor What should the project manager have created to prevent this situation1?
Correct Answer: C
A team charter is a document that is developed in a group setting that clarifies team direction while establishing boundaries. It is developed early during the forming of the team. The charter should be developed in a group session to encourage understanding and buy-in. The team charter has two purposes. First, it serves as a source of information for people who are not part of the team. Second, it serves as a reference for team members. In this case, the project manager is having trouble with meetings not going according to plan and ending in arguments. A team charter could have helped prevent this situation by setting clear expectations for team behavior, roles and responsibilities, and decision-making processes. References: Professional in Business Analysis Reference Materials source and documents