During a kick-off meeting at the start of project execution, the vendor presents a migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live. What should the project manager do?
Correct Answer: B
When a director demands the ability to make the final go/no-go decision about whether the systems go live, the project manager should schedule a meeting with the project sponsor to determine if it is appropriate to accept the director's request. The project sponsor is typically a senior executive in a corporation (often at or just below board level) who is responsible to the business for the success of the project. This meeting would help clarify roles and responsibilities, and ensure that the decision-making process aligns with the project's governance structure. References: https://www.coursera.org/articles/project-management-lifecycle https://www.projectmanager.com/blog/project-director-role