How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
Correct Answer: B
Agile measurements, such as the delivery of incremental working products, can improve upon predictive measurements by providing tangible progress and value at regular intervals. This approach is particularly beneficial when the final stages of a project are delayed, as it ensures that the customer continues to receive functional components of the product. This method aligns with the agile principle of delivering working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale1. References: * 37 Agile Metrics - The Complete Guide for Agile Teams1 * Agile Practice Guide | Project Management Institute2 * Agile project management and the PMBOKguide3