A client comes to the company asking to copy a project that was executed 2 years ago in the same city, with the expectation that the new project will have the same cost and duration. While finalizing the project management plan, the project manager realizes that the baseline costs are much higher than the original project. What could the project manager have done to avoid this?
Correct Answer: A
The project manager could have avoided higher baseline costs by verifying applicable budget inputs related to the project. This involves establishing a baseline that clearly describes the project scope, cost, and schedule1. If deviations from the baseline become necessary, project managers must follow an agreed-upon protocol for communicating issues, determining next steps, and making changes to the plan1. Cost estimation is critical for success in project management because every project manager must estimate all project costs before creating a project budget2. If the project budget is insufficient, it's very likely to face cost overrun2. References: https://www.projectmanager.com/blog/7-tips-for-preventing-cost-overrun-on-projects https://training-nyc.com/learn/pmp-certification/baseline