Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
Correct Answer: C
The burnup chart indicates that the "Completed" work is trailing behind the "Scope," suggesting that the team is not meeting the expectations set by the product owner. This discrepancy can be due to various factors such as underestimation of tasks, unforeseen challenges, or scope changes. It's important for the project lead to address this with the product owner and team to realign expectations, reassess the workload, and implement corrective actions to ensure that project goals are met within the sprint timeframe. References: * A Guide to the Project Management Body of Knowledge (PMBOKGuide) * The PMI Guide to Business Analysis * Business Analysis for Practitioners: A Practice Guide12345.