In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project. What should the project manager do first to meet the product leader's expectations?
Correct Answer: C
In a predictive project approach, milestones are crucial for monitoring progress and ensuring alignment with the project's defined scope and established deadlines. The project manager should first meet with the software team to discuss the feasibility of incorporating monthly milestone reviews as requested by the product leader. This action aligns with the principles of effective communication and stakeholder engagement, which are essential in managing expectations and ensuring project success. By reviewing the possibility of monthly milestones, the project manager can facilitate a clear understanding of the project's progress and make necessary adjustments to meet the product leader's expectations and the project's objectives. References: = The importance of milestones in project management and the need for regular reviews to ensure project alignment with scope and deadlines are well-documented in the PMBOKGuide and PMP resources12. Additionally, the Professional in Business Analysis materials emphasize the significance of stakeholder communication and engagement in project success34.