A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope. What should the project manager do first?
Correct Answer: B
When a key stakeholder requests additional work that is not in the scope, the first action a project manager should take is to evaluate the impact of the requested change. This involves assessing how the change will affect the project's scope, schedule, budget, quality, risk, and benefits. After a thorough evaluation, the project manager should submit a change request. This formalizes the process and ensures that the requested change is documented, evaluated, and approved (or rejected) systematically within the project's change control procedures. References: = The PMBOKGuide outlines the importance of evaluating the impact of scope changes and the process for submitting change requests. It emphasizes that changes should be formally documented and processed through the project's change control system12. This approach is aligned with best practices in project management for handling out-of-scope requests3.