Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments. How should the project manager impartially prioritize the requirements to be integrated?
Correct Answer: D
In situations with conflicting departmental priorities, the project manager should prioritize requirements based on a benefit-cost ratio analysis. This method ensures an impartial and quantitative approach to decision-making. By evaluating the potential benefits against the costs for each requirement, the project manager can objectively determine which requirements will deliver the greatest value to the organization. This approach aligns with best practices in project management and business analysis, which advocate for prioritizing requirements that maximize business value and stakeholder satisfaction123. References: * 5 Steps to Master Requirements Prioritization | ProjectManagement.com1 * Five Requirements Prioritization Methods - Business Analyst Articles2 * How to Prioritize Requirements: A Guide for BAs - LinkedIn3