A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m. What should the project manager do?
Correct Answer: D
When a project requires a significant resource, such as the installation of a call center, it's important for the project manager to conduct an alternative analysis. This analysis will help determine the most effective and efficient approach, whether that's hiring people directly or contracting with a company. The decision should be based on various factors such as cost, time, quality, and the specific needs of the project. References: Project Management Professional (PMP) Reference Materials, Professional in Business Analysis Reference Materials study guide. Please note that the exact documents and page numbers are not provided as the information is based on general project management principles. For more detailed information, please refer to the specific guides and documents mentioned.