After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term. What should the project manager do in order to gather the information needed from stakeholders?
Correct Answer: A
According to the PMBOK Guide, the project manager should collect requirements from all stakeholders, using various techniques such as interviews, focus groups, surveys, etc. The project manager should also document the stakeholder requirements, expectations, and assumptions in the requirements traceability matrix. If some stakeholders are not available for a meeting, the project manager should use other communication methods to reach out to them and gather their input. This will ensure that the project requirements are complete, accurate, and aligned with the stakeholder needs and expectations. References: PMBOK Guide, 6th edition, pages 140-141, 152-153.