A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level. What engagement model should the project manager use for the technical architect role to ensure project success?
Correct Answer: B
Sharing the existing technical architect is a strategic approach that allows for the utilization of their valuable knowledge across multiple projects, including the current one. This engagement model promotes efficient use of resources and expertise within the organization. It enables the technical architect to contribute their specialized skills to the current project while maintaining their responsibilities at the portfolio level. This approach aligns with the principles of resource management and optimization, ensuring that the project benefits from the architect's expertise without compromising their existing commitments123. References: (Composable Engagement Models For Architects - LinkedIn; Composable Engagement Models For Architects - Architecture & Governance Magazine; IT Engagement Models: Definition, Types and Process - Outstaff Your Team).