Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected. What should the project manager do?
Correct Answer: D
An earned value analysis (EVA) is a tool that measures the project performance in terms of scope, schedule, and cost. It compares the planned value (PV), the earned value (EV), and the actual cost (AC) of the project work to determine the variances and the indexes. By conducting an EVA, the project manager can identify the root causes of the project delay and cost overrun, and take corrective actions accordingly. An EVA can also help the project manager communicate the project status and progress to the stakeholders more effectively and objectively. References: (Professional in Business Analysis Reference Materials source and documents) * PMBOK Guide, 6th edition, Chapter 7, Section 7.4.2.1 * PMP Exam Content Outline, June 2019, Domain III, Task 8 * PMP Sample Test Questions, Question 2