A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product. How should the project manager establish the delivery model for this project?
Correct Answer: A
For a multiyear ERP solution project where the business sponsor wants to see value demonstration throughout the project while maintaining the integrity of the final product, the project manager should establish a delivery model that allows for incremental delivery of value. This can be achieved by organizing the project into multiple subsets based on business functions, and delivering each subset as a component of the final product. This approach aligns with the principles of agile and iterative development, which are part of the PMBOK Guide's practices. It allows for early and continuous delivery of valuable software components, enabling the business to realize benefits incrementally, which is crucial for long-term projects such as ERP implementations12. References: * "How Do You Decide Which Project Delivery Approach to Take?" PM Network1. * "Methodologies to implement ERP systems - Are they PMBOK guide compliant?" Project Management Institute2.