An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time. What should the project manager do to help the project team?
Correct Answer: B
In situations where a specialist's on-site presence is impeded by travel restrictions, leveraging virtual technology to facilitate the specialist's guidance remotely aligns with the PMBOKGuide's emphasis on project communications management. The PMBOKGuide acknowledges the importance of communication methods in project management, which includes interactive, push, pull, and virtual communications. Virtual sessions are a form of interactive communication that allows for two-way exchanges of information, making it an effective alternative when face-to-face interactions are not possible. This approach ensures that the project team can still benefit from the specialist's expertise without delay, adhering to the project's time constraints and maintaining progress towards its objectives. References: = The PMBOKGuide and the PMP Examination Content Outline provide guidance on project communication methods and the use of technology to facilitate communication when traditional methods are not feasible12. The Professional in Business Analysis Reference Materials also support the use of various communication channels to ensure project continuity3.