While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What should the project manager do to ensure a smooth delivery of the product?
Correct Answer: B
When a customer introduces new quality standards during the finalization of project management plans, it is essential to align the project's deliverables with these new standards to ensure customer satisfaction and project success. The project manager should collaborate with the client to agree on acceptance criteria that reflect the new quality standards. This agreement will guide the project team in adjusting their work processes and outputs to meet these criteria, thereby ensuring that the final product adheres to the customer's requirements. Involving the client in this process also fosters a shared understanding and commitment to the quality objectives, which is crucial for a smooth delivery of the product. References: The response is based on best practices in project quality management as outlined in the PMBOKGuide and the Professional in Business Analysis (PMI-PBA) reference materials, which emphasize the importance of stakeholder engagement and agreement on project objectives and criteria for acceptance12.