One of the team members is always late to the daily standup meeting. What should the project manager do?
Correct Answer: D
Addressing the issue of tardiness directly with the team member is a proactive approach that aligns with the principles of effective communication and individual respect outlined in the PMBOKGuide. By speaking with the team member, the project manager can understand any underlying reasons for the lateness and work collaboratively to find a solution. This maintains the integrity of the standup meeting as a key communication tool within Agile methodologies and respects the time of all team members. References: The approach of direct communication is supported by the PMBOKGuide's emphasis on timely and effective communication within project teams. Additionally, the Professional in Business Analysis (PMI-PBA) reference materials advocate for addressing individual team member challenges in a manner that supports the overall project objectives and team dynamics12.