A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all. How should the project manager proceed?
Correct Answer: B
The project manager should calculate the costs for each option in each location and compare the net present value (NPV) for each. This is because NPV is a comprehensive financial metric that takes into account both the timing and the amount of cash flows, providing a complete picture of the profitability and financial feasibility of the project. It is a standard method for using the time value of money to appraise long-term projects. By comparing the NPV of each option, the project manager can identify the most financially viable option. References: Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide)-Seventh Edition. Project Management Institute, Inc.