A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects. How can the project manager strategize the use of a hybrid approach to the organization?
Correct Answer: A
In the context of a complex research project with high levels of uncertainty, presenting the benefits of a hybrid approach to key stakeholders is crucial for gaining their support. A hybrid approach combines elements of both predictive (traditional) and adaptive (agile) project management methodologies, allowing for flexibility in planning and execution while still providing structure where needed. This strategy is particularly effective when dealing with projects that have uncertain requirements or that may experience significant changes during their lifecycle. By engaging stakeholders and securing their buy-in, the project manager can ensure that the organization is aligned and supportive of the hybrid approach, which is essential for its successful implementation123. References: * PMBOKGuide - Seventh Edition4 * Hybrid Project Management: The What, Why, and Hows - 4PMTI1 * Agile, Traditional, and Hybrid Approaches to Project Success - PMI3 * Professional in Business Analysis Reference Materials5