A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects What should the project manager do?
Correct Answer: B
According to the PMBOK Guide, the project manager should adapt the project management approach to the development approach and the project life cycle. In a hybrid environment, where some aspects of the project are predictive and some are adaptive, the project manager should balance the level of control and flexibility, and empower the team to make decisions based on the customer feedback and the project objectives. By supporting the decisions of the team and transferring the decision making responsibility to them, the project manager can foster collaboration, innovation, and customer satisfaction. References: PMBOK Guide, 6th edition, page 19-20, section 1.2.3.2 Project Management Approaches and Development Lifecycles.