The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?
Correct Answer: D
The risk register is an artifact that records the identified risks, their probability and impact, their status, and their response plans. It also tracks the risk triggers, which are the indicators or warning signs that a risk is about to occur. By sharing the risk register with the stakeholder, the project manager can show when a risk may potentially become an issue, based on the risk triggers and the risk status. The risk register also helps the project manager and the stakeholder to monitor and control the risks and their impacts throughout the project life cycle. References:
* The PMI Guide to Business Analysis Includes The Standard for Business Analysis, Chapter 4: Business Analysis Planning and Monitoring, Section 4.3.4: Plan Risk Management
* Business Analysis for Practitioners: A Practice Guide, Chapter 4: Planning the Business Analysis Approach, Section 4.6: Risk Management Plan
* Business Analysis Techniques: 72 Essential Tools For Success, Chapter 6: Business Analysis Planning and Monitoring, Section 6.6: Risk Analysis and Management
* Seven Steps to Mastering Business Analysis, Chapter 7: Requirements Analysis, Section 7.4: Risk Analysis