In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
Correct Answer: C
In a highly politicized organizational environment, it is essential for the project manager to actively engage stakeholders to align them with the collective project goal. The PMI standards suggest that promoting a collaborative culture, inspiring stakeholders by setting a positive example, and diligently following the stakeholder engagement process are effective strategies for managing conflicting interests and driving the project towards success. This approach helps in navigating the political landscape by fostering an environment of cooperation and shared objectives. References: = The PMI's "A Guide to the Project Management Body of Knowledge (PMBOKGuide)" and "Business Analysis for Practitioners: A Practice Guide" both emphasize the importance of stakeholder engagement in project management, particularly in complex and politicized contexts12.