A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive. What should the project manager have done to avoid this situation?
Correct Answer: B
According to the PMBOK Guide, requirements elicitation is the process of identifying and communicating with stakeholders to determine what their needs and expectations are for the project. Requirements elicitation helps to ensure that the project delivers value to the stakeholders and meets their requirements. In this scenario, the project manager should have applied requirements elicitation techniques, such as interviews, workshops, surveys, or observation, to involve the stakeholders consistently in the requirements process and to clarify and validate their needs and expectations. This would have helped to avoid the situation of conflicting and changing information from the stakeholders and to gain their buy-in and support for the project. References: PMBOK Guide, 6th edition, page 140-141. PMP Sample Test Questions, question 4. Free PMP Questions and Answers, question 4. Free PMP Practice Exam Questions, question 4.