Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned. What should the project manager do next?
Correct Answer: B
According to the PMBOK Guide, when a change request is received, the project manager should evaluate the impact of the change on the project scope, schedule, cost, quality, risk, and other aspects. The project manager should also consult with the project sponsor and other key stakeholders to obtain their approval or rejection of the change request. The project manager should not proceed with the change without proper analysis and authorization, nor should they reject the change without considering the legal and contractual implications. References: PMBOK Guide, 6th edition, pages 115-116, 134-135, 141-142.