Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
local company is developing a new product and. for the first time, using a remote team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings. How should the project manager address this situation?
Correct Answer: D
The project manager should determine the communication needs, environment, and tools to get the message across to the remote development team. This is part of the Plan Communications Management process, which involves identifying and documenting the approach to communicate most effectively and efficiently with stakeholders1. Evaluating and reassigning the developing tasks to a local vendor who has worked on previous projects (A) is not a viable option since it would disrupt the project schedule, budget, and scope. Documenting the risk in the risk management plan and using contingency reserves to hire a local vendor (B) is also not appropriate since the communication issue is not a risk but a problem that needs to be resolved. Reviewing lessons learned from previous projects and organizational process assets (OPAs) is a good practice, but it is not sufficient to address the current situation. References: * 1: A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition, Chapter 10, Section 10.1.3.1