A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders What document should the project manager use to communicate these requests?
Correct Answer: B
A change log is a document that contains the list of changes that are made during the project. It tracks the progress of each change based on its review, approval, implementation, and closure. A change log is a useful tool for communicating the status of change requests to the stakeholders, as it shows the impact and outcome of each change. A risk log, a backlog, and an issue log are different documents that serve different purposes. A risk log records the identified risks, their probability, impact, and response strategies. A backlog is a list of features or tasks that need to be completed in an agile project. An issue log records the issues that arise during the project, their causes, effects, and resolution. References:
* Change Log - Project Management Knowledge
* Change Log Template - Project Management Docs
* Risks, issues, and changes-help, I'm drowning in logs!