Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager has received an updated earned value analysis report The following are the key findings from the report *Budget at completion = USS1 million *Earned value = US$0 7 million *Actual cost = US$0 75 million *Cost performance index = 0 933 Based on this information, what should the project manager conclude about project performance'?
Correct Answer: C
According to the PMBOK Guide, 7th edition, the cost performance index (CPI) is a measure of the cost efficiency of the project. It is calculated by dividing the earned value (EV) by the actual cost (AC). A CPI of 1 indicates that the project is on budget, a CPI greater than 1 indicates that the project is under budget, and a CPI less than 1 indicates that the project is over budget. In this case, the CPI is 0.933, which means that the project is spending more than planned to achieve the same amount of work. This implies that the project will be difficult to complete as planned, unless corrective actions are taken to improve the cost performance. The other options are incorrect because they do not reflect the current situation of the project based on the CPI value. References: PMBOK Guide, 7th edition, page 267; Earned Value for the PMP Exam; Sample PMP Earned Value Questions