A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
Correct Answer: A
According to the PMBOK Guide, a project manager and project team should select the appropriate work methods and tools based on the project characteristics, such as the product scope, complexity, uncertainty, and delivery approach1. The work methods and tools should also be aligned with the business need and project constraints, such as the budget, schedule, quality, and resources2. Therefore, the result of the discussion should be an agreed-upon work method and tools that should fit the business need and project constraints. References:
* 1: PMBOK Guide, 6th edition, Chapter 4: Project Integration Management, p. 74-75
* 2: PMBOK Guide, 6th edition, Chapter 5: Project Scope Management, p. 131-132