A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable What should the project manager do to resolve this?
Correct Answer: A
According to the PMBOK Guide, 6th edition, section 13.2.2.4, stakeholder engagement assessment matrix is a tool that can be used to identify the current and desired levels of engagement for each stakeholder or stakeholder group. The project manager should use this matrix to plan and implement appropriate strategies to increase the support and minimize the resistance of the stakeholders. One of the strategies is to meet with the stakeholder and discuss the impact of the project deliverable on their interests, needs, and expectations. The project manager should also explain the benefits of the deliverable for the organization and the stakeholder, and address any concerns or issues that the stakeholder may have. By doing so, the project manager can increase the stakeholder's awareness, understanding, and involvement in the project, and foster a positive relationship with them. References: PMBOK Guide, 6th edition, section 13.2.2.4; PMI website