During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)
Correct Answer: D
The PMBOK Guide suggests that conflicts should be addressed early and directly among the affected parties using a collaborative approach. This involves open communication and problem-solving techniques to find a mutually acceptable solution. It is recommended to resolve disputes privately and collaboratively, ensuring that the project manager and team members work together to reach a satisfactory resolution1. References: = PMBOK Guide 7th edition; Conflict Resolution Strategies In Project Management (PMP)1.