A hybrid project team is working on an upgraded version of software for their product owner. The team is also responsible for supporting the existing product and customers. For the last three sprints, the team had to stop their project work and focus on major support items for the product owner. The testers are struggling to cope with the constant changes to the plan, which has resulted in a number of emotional outbursts. How should the project manager proceed?
Correct Answer: D
The project manager should schedule a session with the team to discuss the issues and work with them to define a plan to manage the sprints going forward. This will help to address the team's concerns, resolve the conflicts, and improve the team's morale and performance. The project manager should also communicate with the product owner and other stakeholders to align the expectations and priorities for the project and the support items. The project manager should also use agile principles and practices to adapt to the changing requirements and deliver value to the customer. Requesting a replacement, scheduling a session with the product owner, or asking HR to send the team members to a workshop are not the best ways to proceed, as they may not solve the root cause of the problem, damage the team's trust and cohesion, or delay the project delivery. References: * PMP Exam Content Outline, Domain II: Process, Task 5: Support team members and stakeholders to meet project objectives and stakeholder expectations. * A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition, Chapter 3: Project Performance Domain, Section 3.2: Team Performance, Page 77. * Professional in Business Analysis (PBA) Certification Exam Outline, Domain III: Analysis, Task 5: Validate Requirements, Page 14.