After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project. Which phase of the Tuckman ladder of team formation is occurring?
Correct Answer: C
The project team is in the "Storming" phase of the Tuckman Ladder Model. This phase is characterized by conflict and disagreement, where team members challenge each other, the project, and its leadership. The discomfort among team members and the challenges to the schedule are indicative of this phase. It's a crucial stage where the team starts to address the project's tasks, plans, and ideas, leading to various opinions that can cause conflict. The project manager's role during this phase is to help the team resolve conflicts and disagreements and guide them towards a common understanding and cooperation12. References: * What is the Tuckman Ladder Model? Learn 5 Stages of Team Development * What is the Tuckman Ladder Model? 5 Stages of Team Development.