The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log How should this complaint be addressed?
Correct Answer: D
The best way to address the complaint is to involve the operations director or a representative from the operations team in the agile process. By inviting them to the validation and sprint meetings, they can provide feedback, clarify requirements, and validate the product increments. This will help to ensure that the product meets the performance indicators and the expectations of the operations department. It will also foster collaboration and transparency among the stakeholders and the project team. References: * What is a Sprint Review? | Scrum.org * What Is a Sprint Review? Goals and Tips for Running This Scrum Event * What is a sprint review? 3 steps to better sprint reviews - Atlassian * What is Stakeholder Management? - ProjectManager * What is Stakeholder Management? | A Step-by-Step Guide - Creately