A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be. What should the project manager do?
Correct Answer: A
The Project Management Professional (PMP) emphasizes the importance of leadership styles in project management. It suggests that a project manager should be able to move from one leadership style to another depending on the situation, which is crucial to be extraordinarily effective1. Moreover, the Professional in Business Analysis (PMI-PBA) highlights the role of a project manager in engaging and motivating the team towards a shared vision to achieve together2. Therefore, studying and determining the appropriate leadership style is essential for improving team performance and commitment. References: * Project Management Institute. (2011). Styles of Leadership1. * Project Management Institute. (2009). Essential Leadership Skills Project Managers3. * Project Management Institute. (2011). Effective project leadership: project manager skills and competencies2.