A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan. What should the project manager do?
Correct Answer: B
When a project encounters a risk that was not fully anticipated, and the project manager has developed a new response that deviates from the original plan, it is essential to obtain management approval before proceeding. This ensures that the new approach is aligned with the project's objectives and that management is aware of the changes being made to the risk response plan. The PMBOK Guide highlights the importance of involving project stakeholders, particularly management, when significant changes are proposed1. This is also supported by best practices in business analysis, which advocate for stakeholder engagement and approval in the decision-making process to address risks effectively2. References: * PMBOK Guide, 6th Edition, Project Management Institute. * Professional in Business Analysis (PMI-PBA) resources, Project Management Institute.