Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After 3 days of work, the project manager completed two actions and spent US$80,000. What should the project manager do next?
Correct Answer: C
Given the situation where the project manager has spent $80,000 to complete only two actions in three days, it is clear that both the budget and schedule are not on track as planned. The cost performance index (CPI) and schedule performance index (SPI) are both less than 1.0, indicating that the project is over budget and behind schedule. The CPI is calculated as the earned value (EV) divided by the actual cost (AC), and the SPI is the EV divided by the planned value (PV). In this case, the EV is lower than expected because fewer actions have been completed than planned, and the AC is higher than the EV, leading to a CPI of less than 1.0. Similarly, the SPI is less than 1.0 because the project is behind schedule. Therefore, the project manager should reevaluate and prioritize the remaining actions to maximize the use of the remaining budget and time. This may involve identifying which of the remaining actions are most critical to the project's objectives and finding ways to complete them within the constraints or seeking additional resources or time if necessary. References: PMBOK Guide and standards foundational documents; Professional in Business Analysis (PMI-PBA) reference materials123.