Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?
Correct Answer: A
When a new sponsor joins a project, it is crucial for the project manager to perform a stakeholder analysis to understand the new sponsor's expectations, influence, and level of engagement. This process helps in aligning the project objectives with the new sponsor's vision and ensures that the project artifacts are in line with their expectations. It also aids in establishing communication and building trust with the new sponsor, which is essential for the project's success1. References: = Stakeholder Analysis: Pivotal Practice to Project Success | PMI1