A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member's deliverables do not meet the requirements. What should the project manager do first?
Correct Answer: B
When deliverables do not meet requirements, it is essential to understand the root cause of the issue. The first step should be to engage with the project team to discuss the processes used and identify any misunderstandings or gaps in knowledge. This approach aligns with the PMBOKGuide's emphasis on communication and stakeholder engagement as key aspects of project management. It also reflects the principles of collaboration and continuous improvement found in business analysis practices. References: = PMBOKGuide1, PMI Professional in Business Analysis (PMI-PBA) reference materials2.