A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders. What should the project manager do?
Correct Answer: A
The best course of action is for the project manager to engage with the team member to understand their concerns and work together to redefine the purpose of the report. This approach aligns with the PMI's emphasis on collaboration, communication, and stakeholder engagement as key aspects of effective project management. By reviewing the report's requirements, the project manager can ensure that it serves its intended purpose and is valuable to stakeholders, while also addressing the team member's concerns about its relevance and length. References: = Project Management Professional (PMP)Certification1, PMI Professional in Business Analysis (PMI-PBA)2.