Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information should the project manager provide so that senior management can get a broader view of the project?
Correct Answer: C
Providing a milestones status report to senior management offers a broad view of the project's progress and critical points. This type of report includes information on significant events, deliverables, or achievements at certain points in time, which are essential for decision-making. It helps senior management understand the project's current state, forecast future progress, and make informed decisions based on how the project aligns with strategic objectives. References: * PMBOKGuide - Seventh Edition * The Standard for Project Management * The PMI Guide to Business Analysis