Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document. What should the project manager do to avoid a delay in the project?
Correct Answer: D
In project management, it's important to keep the project moving forward even when key stakeholders are not immediately available. In this case, the project manager should begin discussions with other functional managers first. This allows the project to progress while waiting for the accounting manager. Once the accounting manager is available, their feedback can be incorporated into the solution document. This approach helps avoid delays in the project. References: Project Management Professional (PMP) Reference Materials and Professional in Business Analysis Reference Materials guides and documents. Please refer to the specific sections on stakeholder management and communication management for more details.