A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online, yet some stakeholders lack an understanding of how it will provide value to the organization. What should the project manager do next?
Correct Answer: C
The project manager should coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals. This is because the stakeholders are the ones who will ultimately realize the benefits of the project, and their understanding of how the project will provide value is crucial for its success. By coordinating with the stakeholders, the project manager can ensure that the benefits management plan is understood and agreed upon, and that it aligns with the organization's goals1. References: * How to Effectively Manage Software Development Projects * 4 Phases of the Project Management Lifecycle Explained * The new project manager's survival guide: 20 expert tips to follow * What Does a Project Manager Do in Software Development? - Full Scale