A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints. This request does not match the project manager's expectation, since a program manager is overseeing the remaining work How should the project manager approach the situation?
Correct Answer: D
In situations where there is a disagreement or misalignment of expectations between a project manager and a program manager, it is advisable to schedule a meeting to discuss the different perspectives and agree on a decision. This approach allows for open communication and collaborative problem-solving, ensuring that both parties can express their views and work towards a mutually beneficial resolution. It aligns with the PMI's emphasis on communication and stakeholder engagement as critical components of effective project and program management. References: (Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Seventh Edition and Standards. Project Management Institute.)