Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter. What should the project manager do?
Correct Answer: C
A project charter is a project planning document that sells the project to stakeholders and sponsors. It provides a preliminary delineation of roles and responsibilities, outlines the project's key goals, identifies the main stakeholders, and defines the authority of the project manager. A project charter is essential for any project, regardless of its size or complexity, as it serves the following purposes: * It authorizes the project and grants the project manager the permission to use organizational resources * It serves as a primary sales document that summarizes the project's value proposition and return on investment * It acts as a roadmap that guides the project team and stakeholders throughout the project lifecycle * It helps to manage the project scope and avoid scope creep by establishing the project boundaries and deliverables * It facilitates communication and alignment among the project team, sponsors, and stakeholders by clarifying the project objectives, assumptions, risks, and constraints Therefore, the project manager should explain to the sponsor that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities. Without a project charter, the project may face the following risks: * Lack of clarity and direction for the project team and stakeholders * Misalignment of expectations and goals among the project team, sponsors, and stakeholders * Scope creep and change requests that may impact the project schedule, budget, and quality * Conflicts and disputes over roles, responsibilities, and authority * Reduced stakeholder engagement and support References: * What is a Project Charter? Complete Guide & Examples * How to Write a Project Charter: Examples & Template Included * Project charter - Wikipedia