A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer. What is the appropriate course of action for the project manager to pursue?
Correct Answer: B
In project management, it's important to maintain open and transparent communication with all stakeholders, including unsuccessful bidders. Meeting with the unsuccessful bidder not only provides them with feedback but also maintains a good relationship with them, which could be beneficial for future projects. This approach aligns with the principles of stakeholder management and communication management in project management practices. References: https://bordio.com/blog/how-to-become-a-project-manager/ https://www.indeed.com/career-advice/career-development/how-to-become-a-project-manager